Is the MN transfer switch a Make before Break or vice versa?

I am looking for a transfer switch that will change over from PV/battery to Gen when I start it up, but thinking this through I realized that it might be better to make first in case the fridge is running.

Comments?
Title: Re: Disconnect order Make/Break or Break/make
Post by: Halfcrazy on April 14, 2012, 05:49:28 AM
All of our switches are Break before Make. You would likely get bad things happening if it was Make before Break do to back feeding.


Ryan
Title: Re: Disconnect order Make/Break or Break/make
Post by: Westbranch on April 14, 2012, 02:02:18 PM
thanks Ryan, so how does one mange the 'break' on appliances that are 'in motion' when you 'break' without causing hiccups?

I was looking at some auto-transfer switches and I saw 14 mili-seconds for switch over time, which seemed , to me , to be quite seamless. 